“Prudent and efficient:” Regulator gives green light to make Marinus Link a reality

Plans to build a new sub-sea electricity transmission link between Tasmania and mainland Australia are all but locked in after a revenue proposal for early works for the controversial project was given the green light by the regulator.

The Australian Energy Regulator on Wednesday published a determination paving the way for Marinus Link to
recover the costs for designing and planning the 750MW undersea cable through to a final investment decision.

The determination approves “prudent and efficient capital expenditure” of $196.5 million and finds the proposed scope of works is consistent with the energy market rule maker’s definition of early works.

The AER says Marinus Link has proposed $128.9 million (nominal) of capex for its early works activities after a deduction of grant funding of $67.6 million. It also notes that the proposal included an independent review in support of the expenditure.

“In assessing the proposal, we reviewed Marinus Link’s initial submission, identified and issued several information requests to better understand the structure and cost of the proposal, met with Marinus Link to discuss the proposal, and took into account stakeholder views.

“On the basis of this review, we consider Marinus Link’s early works expenditure is prudent and efficient,” the AER says.

Marinus Link CEO Caroline Wykamp says the determination shows Marinus Link is not spending more than necessary – a criticism that continues to dog the project – and gives the green light to make it a reality.

The cost of delivering Marinus Link – crucial to the so-called “Battery of the Nation” project – has been a major point of contention, after an effective doubling of the price of the originally proposed dual-cable 1500MW project.

With analysts and green campaigners already questioning the project’s viability – and justifications – the Tasmanian government in July appeared to be losing its nerve, publicly questioning the link’s future over its long-term cost to Tasmanians.

In response, the federal and Tasmanian governments struck a deal in September to effectively cut the capacity of the sub-sea link in half, to just one 750MW cable, and for the federal government to take a bigger stake to reduce the financial burden on Tasmania.

The governments said the scaled down project would now cost between $3 billion and $3.3 billion, potentially more than the $3 billion estimate for the entire project made just two years ago – while still delivering two-thirds of the anticipated benefit.

“Today’s determination shows that Marinus Link is not spending more than what is necessary to plan the project,” Wykamp said in a statement on Wednesday.

“Thanks to grant funding from the Australian and Tasmanian governments, the cost to consumers will be even further reduced.

“Importantly, until Marinus Link is commissioned, costs will not be recovered from consumers.”

The decision from the AER is unlikely to be welcomed by critics of the project, who describe it as a boondoggle, even when cut in half.

Bruce Mountain, director of the Victoria Energy Policy Centre, has argued that Marinus will be a dead-weight, facilitating a trade energy arbitrage in which Tasmania has no competitive advantage while driving up electricity prices through increased transmission charges.

Christine Milne, the former leader of The Greens, and now a spokesperson for the Bob Brown Foundation, is also unconvinced that the downsized project is worth the price tag. “One for the price of two, what a bargain!” she told AAP in September.

Marinus Link will submit a second proposal to the AER early next year for ‘construction costs’. A determination on the proposal is expected in late 2024, marking one of the project’s final milestones before final investment decision.

Comments

One response to ““Prudent and efficient:” Regulator gives green light to make Marinus Link a reality”

  1. RobertO Avatar
    RobertO

    Hi All,

    Below is a discussion on VAWT verses HAWT. Some time ago the designers of VAWT ran headlong into the support bearing (simply a mechanical issue which is still valid today, nobody manufactures a unit that is very large)!

    Now the person I have called a very STUPID (Dave2020) insist that his new VDRPP can be powered by a VAWT, (and look at the sizes of VAWT, measured in Watts) and as such I can also use a bladder 100 meters below sea level to power a pelton generator above sea level and as such I can do away with all HVDC at sea (including the connection to Europe)?

    A bladder at 100 metres below sea level can not supply anything to a pelton generator above sea level (that is just simple physics), and there is no logical reason to even consider an accumulator in the system! That a design issue (and no I will not explain, if you don’t understand simple physics then you have no hope in design)!

    Has he actually come up with a VDRPP, I see nothing in his replies that tell me, or gives me any hope that this is a possibility (dreams of a perpetual motion machine, are just dreams)! If the power system is in Watts then the water flow will be in millilitres and to run a pelton generator you need cubic meters per second!

    So Dave2020 you understanding of many things are devoid of logical thinking (just because somebody publishes a claim does not make it true or factual)!

    Many of your claims are based on half truths (misinformation is a better word to use)!

    Eg “when the UK and Europe wind supplies are both full then the HVDC interconnectors are not able to transfer any energy, this is absolutely correct, but how often does that occur, 2% of the time, so what the other 98% (time matters)

    Another claim, these companies get paid £millions but consumers get nothing (reliably of supply, cheaper supply)!

    You actually are a waste of space, which is why I have deleted you!

    Goodbye for ever

Get up to 3 quotes from pre-vetted solar (and battery) installers.